8.1.1 The Contractor has implemented environmental mitigation measures and requirements as stated in the EIA Reports, the EP and the EM&A Manuals. The implementation status of the mitigation measures during the reporting month is summarized in Appendix J. Status of required submission under the EP during the reporting period is summarized in Table 8.1.
Table 8.1 Status of Required Submission under Environmental Permit
|
EP Condition |
Submission |
Submission Date |
|
EP-337/2009 |
||
|
Condition 2.3 |
Management Organization of Main Construction Companies |
18/12/2015 |
|
Condition 2.4 |
Design Drawing of the Project |
18/12/2015 |
|
Condition 2.11 |
Landscape Mitigation Plan(s) |
18/12/2015 |
|
Condition 3.3 |
Monthly EM&A Report (January 2017) |
17/02/2017 |
|
EP-339/2009/A |
||
|
Condition 2.4 |
Management Organization of Main Construction Companies |
18/12/2015 |
|
Condition 2.5 |
Design Drawing of the Project |
18/12/2015 |
|
Condition 3.3 |
Monthly EM&A Report (January 2017) |
17/02/2017 |
|
EP-451/2013 |
||
|
Condition 2.3 |
Management Organization of Main Construction Companies |
18/12/2015 |
|
Condition 2.4 |
Design Drawing of the Project |
18/12/2015 |
|
Condition 2.5 |
Landscape Mitigation Plan(s) |
18/12/2015 |
|
Condition 2.10 |
Supplementary Contamination Assessment Report |
18/12/2015 |
|
Condition 3.3 |
Baseline Monitoring Report |
12/02/2016 |
|
Condition 3.4 |
Monthly EM&A Report (January 2017) |
17/02/2017 |