Summary of Site Audit in the Reporting Month

Parameters

Date

Observations and Recommendations

Follow-up

Air Quality

12 October 2017

 

Open stockpiles of materials shall be properly covered with impermeable sheeting to enhance dust suppression (Portion I). Impermeable sheeting shall be provided.

 

The item was rectified by the Contractor and inspected on 18 October 2017.

12 October 2017

 

Contractor was reminded that handling or storage of bulk cement should be carried out in an enclosed system or placed in an area sheltered with the top and the three sides (Zone 2, 4)

 

The item was rectified by the Contractor and inspected on 18 October 2017.

26 October 2017

Contractor was reminded that stock of more than 20 bags of cement should be covered by impervious sheeting (Zone 2).

The item was rectified by the Contractor and inspected on 2 November 2017.

Noise

4 October 2017

 

Contractor was reminded to provide acoustic fabric for breaking tip (Zone 1).

 

The item was rectified by the Contractor and inspected on 12 October 2017.

12 October 2017

 

The door of air compressor shall be closed to reduce noise impact (Zone 4).

 

The item was rectified by the Contractor and inspected on 18 October 2017.

Water Quality

 

NA

 

Chemical and Waste Management

4 October 2017

Chemical containers shall be stored on drip tray (Zone 4). Drip Tray shall be provided.

The item was rectified by the Contractor and inspected on 12 October 2017.

18 October 2017

Contractor was reminded to store chemical container properly (Zone2 and Zone 4).

 

The item was rectified by the Contractor and inspected on 26

October 2017.

 

26 October 2017

 

Chemicals should be stored in drip tray properly (Zone 4). Drip tray shall be provided.

 

The item was rectified by the Contractor and inspected on

2 November 2017.

Land Contamination

NA

Landscape and Visual Impact

12 October 2017

Stockpile at Portion I should be properly covered asap.

The item was rectified by the Contractor and inspected on 18 October 2017.

12 October 2017

 

Building material at Zone 4 should be properly stored and covered. (Cement) It shall be tidy up immediately.

 

The item was rectified by the Contractor and inspected on 18 October 2017.