10.1.1 24-hour TSP impact
monitoring and construction noise monitoring were carried out in the reporting
month, no Action / Limit Level exceedance was recorded during the period.
10.1.2 No complaint of air quality was received. Therefore, no impact 1-hour TSP
monitoring was conducted in the reporting month.
10.1.3 Five environmental site
inspections were carried out in the reporting month. Recommendations on
mitigation measures on air quality, water quality, noise, waste management and
landscape and visual impact were given to the Contractor for remediating the
deficiencies identified during the site inspections.
10.1.4 Five weekly Landscape and Visual Site audits were carried out on 2, 9, 15, 23 and 30
November 2017 and two of
them, 9 and 23 November 2017 were carried out by a Registered Landscape
Architect in the reporting month. The weekly Landscape and Visual Impact
reports were counter-signed by IEC as according to the requirement of EM&A
Manual (AEIAR-130/2009).
10.1.5 Referring to the Contractor’s information, no environmental complaint, notification
of summons and successful prosecution was received in the reporting month.
10.2
Comment and Recommendations
10.2.1 The recommended environmental mitigation measures, as proposed in the EIA
reports and EM&A Manuals shall be effectively implemented to minimize the
potential environmental impacts from the Project. The EM&A programme would effectively monitor the environmental
impacts generated from the construction activities and ensure the proper
implementation of mitigation measures.
10.2.2 According to the environmental audit performed in the reporting month,
the following recommendations were made:
Air Quality Impact
l Plants and equipment should be
well-maintain to prevent dark smoke emission. Contractor should maintain plant
and equipment to prevent dark smoke emission.
Construction Noise Impact
l
No specific observation was identified in the reporting month.
Water
Quality Impact
l
No specific observation was identified in the reporting month.
Chemical and Waste Management
l Contractor was reminded to store
chemicals in drip tray. Drip tray shall be provided.
Land
Contamination
l
No specific observation was identified in the reporting month.
Landscape and Visual Impact
l
No specific observation was identified in the reporting month.
General Condition
l No
specific observation was identified in the reporting month.
Permit / Licenses
l No
specific observation was identified in the reporting month.