Summary of Site Audit in the Reporting Month

Parameters

Date

Observations and Recommendations

Follow-up

Air Quality

7 December 2017

 

Open stockpile should be covered with impermeable sheeting to facilitate dust suppression (Portion I). Open stockpile shall be covered with impermeable sheeting Properly.

 

The item was rectified by the Contractor and inspected on 14 December 2017.

7 December 2017

 

Dusty materials have accumulated on the ground surface on Portion I. Regular cleaning should be carried out.

 

The item was rectified by the Contractor and inspected on 14 December 2017.

Noise

7 December 2017

 

Acoustic fabric should be used for the operation of breaking tip (Zone 4). Acoustic fabric shall be provided to reduce noise.

 

The item was rectified by the Contractor and inspected on 14 December 2017.

28 December 2017

When operating breaking tip, acoustic fabric should be used to reduce noise generation (Zone 2). Acoustic fabric shall be provided.

The item was rectified by the Contractor and inspected on 4 January 2018.

Water Quality

 

14 December 2017

 

 

Untreated construction runoff was found flow into the drainage (Zone 1). Contractor should prevent untreated construction runoff discharge into drainage, mitigation measures shall be carried out.

 

The item was rectified by the Contractor and inspected on 20 December 2017.

Chemical and Waste Management

 

NA

 

Land Contamination

NA

Landscape and Visual Impact

7 December 2017

 

Stockpiling at Portion I should be properly covered. Contractor should rectify ASAP.

 

The item was rectified by the Contractor and inspected on 14 December 2017.

General Condition

 

NA