Table
8.1         Status
of Required Submission under Environmental Permit
| EP
  Condition | Submission | Submission
  Date | 
| EP-337/2009 | ||
| Condition 2.3 | Management Organization of Main Construction Companies | 18/12/2015 | 
| Condition 2.4 | Design Drawing of the Project | 18/12/2015 | 
| Condition 2.11 | Landscape Mitigation Plan(s) | 18/12/2015 | 
| Condition 3.3 | Monthly
  EM&A Report (December 2018) | 14/01/2019 | 
| EP-339/2009/A | ||
| Condition 2.4 | Management Organization of Main Construction Companies | 18/12/2015 | 
| Condition 2.5 | Design Drawing of the Project | 18/12/2015 | 
| Condition 3.3 | Monthly
  EM&A Report (December 2018) | 14/01/2019 | 
| EP-451/2013 | ||
| Condition 2.3 | Management Organization of Main Construction Companies | 18/12/2015 | 
| Condition 2.4 | Design Drawing of the Project | 18/12/2015 | 
| Condition 2.5 | Landscape Mitigation Plan(s) | 18/12/2015 | 
| Condition 2.10 | Supplementary Contamination Assessment Report | 18/12/2015 | 
| Condition 3.3 | Baseline Monitoring Report | 12/02/2016 | 
| Condition 3.4 | Monthly
  EM&A Report (December 2018) | 14/01/2019 |